The rehabilitation of the Ben Sawyer Bridge respects the following visual and natural environmental considerations:
- The bridge is being rehabilitated on the existing alignment with no new right-of-way and only a slight shift in the roadway centerline.
- No temporary or permanent fill is being placed in the critical area wetlands during construction.
- An access trestle is being used during construction to minimize construction impacts to critical areas. This trestle allows daily tidal inundation in the construction zone.
- Construction of the new swing span is being completed off-site to reduce the impacts to wetland areas.
- Marsh areas impacted by the access trestle will be returned to original contours, re-vegetated, and monitored after construction.